1. Initial cutting is carried out at green-concrete stage.
2. Final cut is done after 21 to 28 days.
3. Sealant is done on bone dry surface, generally after 1 or 2 days, i.e. between 30th and 35th day.
We help you in selecting & negotiating sealant manufacturers, also we optimize sealant consumption to suit & qualify various tests at site. We conduct field test on trial patch to technically ratify the sealant suitability.
We also undertake complete contract with sealant.